About this document
Cost Estimation for SFCA Line Item 3.1-25-650 by Tony Lee is a document available to read on EtoBox.
This document provides solutions to an in-class exercise estimating construction costs. It calculates the unit costs and total cost to complete 10 million square feet of a construction item. It then factors in production efficiencies reported by the contractor, averaging them to 72.5%. The expected total cost accounting for the lower efficiency is estimated to be $130,758,621.
- Author
- Tony Lee
- Language
- EN